# Software handover after an acquisition: what changes hands, and how

Source: https://techduediligence.co/insights/software-handover-after-acquisition/

Signing transfers ownership on paper. Control of the software transfers later, one account at a time, when someone changes the owner of a repository, moves a domain or replaces a password. A handover run from a checklist, with each item verified and signed off by both sides, is how you make sure the second transfer matches the first.

## Key points

- Separate what can be held in escrow, such as code, documents and agreements, from what can only be transferred live, such as accounts, domains and credentials.
- Draft the handover checklist before closing, from the inventory of assets produced in technical due diligence.
- Verify each item by using it, not by receiving it: log in, deploy, renew, restore.
- Record who transferred what, who checked it and when, and have both sides sign.

## Why handover is a separate job from closing

Closing is a legal event. Documents are signed, money moves and title passes. Handover is an operational process carried out by engineers and administrators over the following days or weeks, and no clause in the agreement performs it for you.

In a share purchase less has to move, since the company still owns its accounts. Control still has to change. Founders often registered early services in their own names, departing staff hold administrator rights, and the only person who knows the registrar password may be leaving with the deal.

In an asset purchase everything has to move, and whatever is missed stays with a seller that may soon cease to exist.

The failures are mundane. A domain is registered to a founder's personal email address. The root login of the cloud account is protected by a code generator on a former employee's phone. The mobile app is published from an agency's developer account. Each is simple to fix in the week after closing and hard to fix a year later, when the relationship has cooled and the people have moved on.

## What can sit in escrow and what cannot

Escrow holds copies. Source code at a defined state, documentation, scan results and executed agreements can be deposited with a neutral party, checked for integrity and released when the agreed conditions are met. That protects both sides during the transaction and creates a record of what was transferred, as described in [the closing package](/insights/ip-package-at-closing/).

Live assets cannot be deposited in that way. A cloud account is a continuing relationship with a provider. A domain is an entry in a registry. A password is useful only while it is valid, and it ought to be changed the moment control passes.

A complete transfer therefore needs two mechanisms: a sealed package for everything that can be copied, and a checklist for everything that must change hands in other companies' systems.

## The checklist, by category

A handover checklist is specific to the product, but the categories recur.

| Category | Typical items | Evidence that it is done |
|---|---|---|
| Repositories | Code hosting organization, every repository including archived ones, pipelines, package registries | Buyer is owner, seller's administrators removed, code matches the closing state |
| Domains and DNS | Registrar accounts, DNS zones (the domain's address records), certificates | Buyer's entity is registrant, buyer has edited a record, renewal is on buyer's payment method |
| Cloud accounts | Owner login, billing, organization settings, backups | Buyer signs in as owner with its own second factor, billing moved, former users removed |
| Credentials and keys | API keys, signing keys, database and encryption keys | Each rotated after transfer, old values revoked, services still running |
| Third-party services | Payments, email delivery, monitoring, analytics, app stores | Ownership changed or new account opened, integration tested |
| Contracts | Supplier, license and customer agreements | Assignment or consent on file, notices sent |
| Knowledge | Runbooks, architecture notes, release procedure | Buyer's engineer performs a release without help |

The inventory compiled in diligence is the natural source for this list.

## Verification: use it, do not just receive it

A password in a document is not a transfer. An item is transferred when two statements are true: the buyer can perform the relevant action alone, and the seller can no longer perform it.

That gives a simple test for each line. For a repository, the buyer pushes a change and the seller's access is refused. For a domain, the buyer edits a record and sees it take effect. For a release pipeline, the buyer's engineer ships a small change to production.

Order matters. Transfer ownership first, verify, then rotate every secret, then remove the former users. Rotation is not optional: every key and password known to the seller's staff should be replaced, including those embedded in configuration and those left in the code's history. The reasons are set out in [secrets in source code and git history](/insights/secrets-in-source-code/).

## Dual sign-off and logging

Each item should be closed by both sides. The seller transfers it and provides evidence. The buyer verifies it. Both confirm.

Each side has an interest in this. The seller obtains a discharge: proof that it delivered what the agreement required, which matters where a final payment or the release of a holdback depends on completion. The buyer obtains proof of what it received and on what date, which matters if a later dispute turns on the state of an asset at transfer.

The log should record who did what and when, and be kept with the transaction record.

## Timing and the people who leave

Two practical points decide whether a handover goes well.

Begin before closing. Agree the checklist, identify every account held in an individual's name and settle the order of work while the seller's team is still in place. The companion list for the day itself is in [a closing-day checklist for software transactions](/insights/closing-day-checklist-software/).

Link the handover to something the seller cares about. Where the agreement ties a payment or a release to completion of the checklist, the work gets done. This is general information and not legal advice, and the rules on assigning contracts and accounts differ by jurisdiction.

## How we approach it

We treat closing as two steps. On closing day a final full scan runs, both sides sign off, and what the transaction transfers is sealed into a single IP Package: source code at closing state, final scan results and findings register, chain-of-title evidence and clause map, license manifest and software bill of materials (SBOM), and the executed transfer agreements. It is stored immutably and retained for three years in the evidence vault.

What cannot sit in escrow then changes hands through a structured handover, which is part of our Professional and Complete engagements. Repositories, domains, credentials, cloud accounts and contracts are transferred against a checklist. The seller transfers each item with evidence, your team verifies it, and both leads sign off. Every step is recorded in an audit trail that both sides can see.

Our page [for acquirers](/for-acquirers/) describes the engagement, and [escrow and the IP Package](/escrow-and-ip-package/) explains the closing mechanics.

## Questions we are asked

### How long should a handover take?

With a checklist agreed before closing, most accounts, domains and repositories can be transferred and verified within days. Contracts that require a third party's consent, and accounts that a provider will not reassign, take longer.

### Should credentials be put into escrow with the code?

As a rule, no. A credential deposited weeks before closing may no longer work on the day, and it is an exposure for as long as it sits there. Transfer control of the account live, then replace the credential.

### What if an account cannot be transferred?

Some providers do not allow an account to move from one legal entity to another. The usual answer is to open a new account in the buyer's name and migrate the product to it, with the seller's help. Identify these cases before closing, because a migration is a project and needs its own line in the plan.