The technology 100-day plan, from diligence findings to first actions

The first hundred days after closing set the pattern for the holding period. The technology part of the plan should come directly from the diligence findings, with each item costed, sequenced and given an owner. This article explains how to make that conversion and how to confirm the work was done.

6 min readUpdated Codekeeper Transaction Services

Why the plan starts in diligence

By closing, the buyer has paid for a detailed account of the target's technology. In many transactions that account is filed with the deal documents, and the new owners begin a fresh assessment a few months later. The knowledge is paid for twice and the first months are lost.

Technical due diligence done properly already contains the plan in outline: a register of findings, each with a severity and an estimate of the effort to fix it. The same estimates fed the valuation, so the plan is also the budget the investment committee approved. Starting from anything else breaks the link between what was priced and what is done.

There is also a practical reason to move quickly. Just after closing the seller is still cooperative, any holdback is still unpaid, and the management team expects change. Requests that are easy in the first month, such as a former contractor's signature, get harder with each month that passes.

Turning findings into work items

A finding describes a condition. A work item describes a change. Converting one into the other takes four steps.

  1. Group by root cause. Twelve outdated libraries are not twelve tasks. They are one: put a routine for updating dependencies in place and clear the backlog.
  2. Decide the treatment. Each finding is fixed now, fixed within the first year, accepted and monitored, or closed with no action. Accepting a finding is legitimate when the cost of fixing exceeds the risk, provided the decision is written down.
  3. Estimate the effort. Express it in engineer-months and as a cost band, and say whether the existing team or outside help will do the work.
  4. Define done. State the observable result: the component is no longer in the build, the agreement is on file, the restore test passed.

The fourth step is the one most often skipped. For how to weigh which debts deserve treatment at all, see technical debt in M&A.

What belongs in the first hundred days

The first hundred days are for work that reduces risk quickly or that will only get harder. In rough order of priority:

  • Ownership gaps. Missing assignments from contractors and former employees, collected while the seller still has reason to help. See contractor-written code and the assignment that was never signed.
  • Access and control. Transfer of repositories, domains, cloud accounts and credentials, and replacement of any keys or passwords found in the code. The mechanics are in the handover.
  • Serious security exposure. Vulnerabilities that can be exploited from outside, and systems without working backups.
  • Dependence on individuals. Documentation and shared responsibility for the modules only one person understands.
  • License problems with real exposure. A copyleft component in distributed software, or commercial licenses that do not survive a change of control.
  • Baselines. Measurements of cost, performance and release frequency, so later improvement can be shown.

Large changes do not belong here. Rewriting a core module, moving to another cloud provider and reorganizing the engineering team are decisions to prepare in the first hundred days and to start afterwards, once the new owners understand the business. A plan that opens with a rebuild usually stalls the roadmap and unsettles the team.

Estimating effort honestly

Every engineer-month spent on remediation is one not spent on the product. The plan has to show both, or it will be abandoned the first time a customer deadline competes with it.

State estimates as ranges, with their assumptions. An upgrade that takes three engineer-months if the automated tests are reliable may take six if they are not.

WindowTypical content
Days 1 to 30Handover of access, replacement of exposed credentials, missing assignments signed, urgent security fixes
Days 31 to 60Upgrades of vulnerable dependencies, backup and recovery test, documentation of concentrated knowledge
Days 61 to 100License remediation, cost and performance baselines, decision paper on any larger architectural work

The table is an illustration, not a template. The right sequence depends on what the review found.

Verifying that the fixes were made

Status reports drift toward green. The evidence that a fix was made is in the same place the finding came from: the code, the configuration and the contracts.

Verification means repeating the check that produced the finding. The vulnerable library is no longer in the build. The key that sat in the repository has been replaced and no longer works. The signed assignment is on file and covers the code the contractor wrote. A re-scan answers most of these questions quickly and gives the board a simple measure: findings open at closing, and findings closed and verified since.

Verification also matters for money. Where a holdback or a deferred payment depends on remedial work, both sides need an objective test of whether the work was completed. The transaction documents govern how that operates. This is general information and not legal advice.

Who owns the plan

The plan belongs to the company's technology leader, not to the fund. An operating partner or board member should review progress regularly, but a plan imposed from outside is carried out slowly.

Ownership is easier when the findings were never in dispute. If management saw each finding during diligence and had the chance to respond, the plan starts from agreed facts. If the chief technology officer first sees the list after closing, the first month goes on arguing about it.

How we approach it

Every report we produce prices the remedial work, as effort in engineer-months and as a cost band. In our analyst-verified and expert reports, each material finding is paired with the market-standard remedy and the work is sequenced into a plan for the first hundred days. This is data-backed negotiation support, not advisory. Completed fixes are verified by re-scan, so progress is measured against the code.

Because the seller responds beside each finding during the review, on the record, management has already seen the list when the plan begins. At closing, the final scan results and findings register are sealed into the IP Package and retained for three years in the evidence vault.

On Professional and Complete engagements there is also a structured handover of repositories, domains, credentials, cloud accounts and contracts against a checklist with dual sign-off. The service is described on our technical due diligence page, and arrangements for funds on our page for funds.

Questions we are asked

Should the plan be shared with management before closing?

In most cases yes, because management will carry it out. In our engagements the seller's team sees each finding and responds on the record, so the plan does not come as a surprise.

How much engineering capacity should remediation take?

There is no general rule, because it depends on what was found and on the roadmap. We report the effort in engineer-months so that the board and management can weigh it against the product work it displaces.

How do we know a fix was really made?

By repeating the check that found the problem. We verify completed fixes by re-scan, and the findings register sealed at closing records the starting point.

This article is general information for people working on software transactions. It is not legal, financial or insurance advice.